Jump to Navigation

Order in Appeal No.156 of 2013

Summary: 

Consumer applying for electricity connection at 33 kV level with a contracted demand of 1501 kVA -- Taking supply in a rescheduled manner in three phases -- DISCOM mentioning levy of energy charges at 11 kV level for the first two phases when the released demand is below 1501 kVA as a condition for release of supply in phased manner -- Consumer accepting the same at the time of release of supply but contesting it later on -- Held not valid



Main menu 2

about seo